C_TSCM42_67 Production Planning and Manufacturing Exam Summary
● Exam Name: SAP Certified Application Associate – Production Planning
& Manufacturing with SAP ERP 6.0 EHP7
● Exam Code: C_TSCM42_67
● Level: Associate
● Exam Price: $550 (USD)
● Duration: 180 mins
● Number of Questions: 80
● Passing Score: C_TSCM42_67 - 63%
● Reference Books: SCM240,
SCM310,
SCM300,
SCM130,
PLM114,
TERP50,
TERP01,
SCM365
● Schedule Exam: SAP
Training
● Sample Questions: SAP PP Certification Sample Question
● Recommended Practice: SAP PP
Certification Practice Exam
Exam Syllabus: C_TSCM42_67 SAP ERP Production Planning and Manufacturing (PP) Certification Practice Exam
1. Material and Capacity Requirements
Planning
Characterize
production-relevant planning functionality.
Books: SCM240, SCM365 OR TSCM40, TSCM42
2. Material Requirements Planning
(PP-MRP)
Explore
material requirements planning functions.
Books: SCM240 OR TSCM40, TSCM42
3. Production Orders Advanced
(PP-SFC)
Configure
production order functionality.
Books: SCM310 OR TSCM40, TSCM42
4. Lean Manufacturing (PP-REM,
PP-KAB)
Outline
the highlights of repetitive manufacturing and kanban.
Books: SCM300, SCM130 OR TSCM40, TSCM42
5. Master Data (LDM)
Set
up master data for production planning and manufacturing.
Books: PLM114 OR TSCM40, TSCM42
6. Production Orders Basics (PP-SFC)
Apply
production order functionality.
Books: SCM310 OR TSCM40, TSCM42
7. Application Overview and
Background
haracterize
the interplay of master data, planning, ATP, and production functionality.
Books: TERP50, SCM240, SCM300, SCM130 OR
TSCM40, TSCM42
8. Basics on SAP Business Processes
(E-Learnings)
Outline
the scope of SAP SCM business processes.
Books: TERP01, TERP50 OR TSCM40, TSCM42
9. Process Orders (PP-PI)
Identify
specific properties of process orders.
Books: SCM300, SCM130 OR TSCM40, TSCM42
SAP C_TSCM42_67 Certification Sample Questions and Answers
To make you familiar with Production Planning and Manufacturing (C_TSCM42_67) certification exam structure, we have prepared this sample question set. We suggest you to try our Sample Questions for PP C_TSCM42_67 Certification to test your understanding of SAP C_TSCM42_67process with real SAP certification exam environment.
C_TSCM42_67Production Planning and Manufacturing Sample Questions:-
01. You
want to procure your material components based on a forecast for the finished
material derived from historical sales. When customers order, you produce the
finished product and reserve it for that particular order.
Which
is the appropriate planning strategy to use?
Please
choose the correct answer.
a) Production by lot size (30)
b) Planning without final assembly (50)
c) Planning with final assembly (40)
d) Make-to-order production (20)
Answer: b
02. In
which ways can you implement confirmations for production orders?
There
are 2 correct answers to this question.
a) Through a SAP Manufacturing Intelligence
and Integration (SAP MII) server
b) Through the Advanced Planning and
Optimization (APO) component
c) Through the SAP Integrated Business
Planning (SAP IBP) cloud solution
d) Through automatic process messages using
SAP NetWeaver Process Integration (PI)
Answer: a, d
03.
Which object in customizing controls the determination of planned total
overhead process costs for production orders?
Please
choose the correct answer.
a) Cost log
b) Accounting type
c) Costing variant
d) Settlement profile
Answer: c
04. For
which planning strategy does the reduction of planned independent requirements
always occur with the goods receipt?
Please
choose the correct answer.
a) Planning with final assembly (40)
b) Gross requirements planning (11)
c) Planning without final assembly (50)
d) Net requirements planning (10)
Answer: b
05.
What happens when a repetitive manufacturing planned order is assigned to a
production line in the planning table?
There
are 2 correct answers to this question.
a) The planned order generates capacity
requirements.
b) The planned order is converted to a
production order.
c) The system status of the planned order changes.
d) The planned order type changes.
Answer: a, d
06. The
settings for MRP can be maintained at different levels. If settings have been
maintained in different places, in which sequence does the system search for
the MRP settings?
Please
choose the correct answer.
a)
Plant Settings → MRP Group → Material Master
b)
Material Master → Plant Settings → MRP Group
c)
Material Master → MRP Group → Plant Settings
d)
MRP Group → Material Master → Plant Settings
Answer:
c
07. How
can you limit the number of master data objects to be created when the
manufacturing process is the same for many different products?
Please
choose the correct answer.
a) By creating routings with alternative
sequences
b) By assigning the same production version to
different materials
c) By assigning different materials to the
same routing
d) By creating routings with parallel
sequences
Answer: c
08.
Which elements are included in the structure of the batch where-used list?
There
are 3 correct answers to this question.
a) Purchase orders
b) Planned orders
c) Transfers from batch to batch
d) Stock transfers
e) Collective orders
Answer: a, c, d
09.
Which of the following are prerequisites for running MRP in a plant?
There
are 3 correct answers to this question.
a) Assign a valid planning strategy
b) Set up the planning file
c) Activate requirements planning
d) Configure MRP groups
e) Maintain plant parameters
Answer: b, c, e
10.
Which of the following options can you use for automatic line loading of
planned orders on available production lines?
There
are 3 correct answers to this question.
a) Planning table
b) Quota arrangement
c) Sequencing
d) Selection method
e) PP/DS heuristics
Answer: b, d, e