C_TS412_2021 S/4HANA Project Systems Exam Summary
- Exam Name: SAP Certified Application Associate - SAP S/4HANA Project
Systems
- Exam Code: C_TS412_2021
- Level: Associate
- Exam Price: $500
- Duration: 180 mins
- Number of Questions: 80
- Passing Score: 68%
- Reference Books:
- S4120 (SAP S/4HANA 2021)
- S4121 (SAP S/4HANA 2021)
- S4122 (SAP S/4HANA 2021)
- S4123 (SAP S/4HANA 2021)
- Schedule Exam: SAP Training
- Sample Questions: SAP S/4HANA Project Systems Certification Sample Question
- Recommended Practice: SAP S/4HANA Project Systems Certification Practice Exam
Exam Syllabus: C_TS412_2021 SAP Certified Application Associate - SAP S/4HANA Project Systems
1. Project Structures
Name
the components of Work Breakdown Structure, Network and activities, Milestones
Books:
● S4121 (SAP S/4HANA 2021)
● S4122 (SAP S/4HANA 2021)
2. Material
Explain
Work breakdown structure BOM, BOM PS Interface, component assignment in the
network, material procurement
Books:
● S4122 (SAP S/4HANA 2021)
3. Cost & Budgets
Describe
procedures for establishing budgets and reporting costs
Books:
● S4123 (SAP S/4HANA 2021)
4. Dates
Describe
the importance of various dates which can be tracked for projects
Books:
● S4122 (SAP S/4HANA 2021)
5. Revenues and Payments
Describe
the characteristics of Revenues & Payments.
Books:
● S4123 (SAP S/4HANA 2021)
6. Resources
Describe
how the Capacity Planning process is carried out.
Books:
● S4122 (SAP S/4HANA 2021)
7. Reporting
Determine
general reporting requirements and report types for SAP S/4HANA Project System.
Books:
● S4120 (SAP S/4HANA 2021)
SAP C_TS412_2021 Certification Sample Questions and Answers
To make you familiar with S/4HANA Project Systems
(C_TS412_2021) certification exam structure, we have prepared this sample
question set. We suggest you to try our Sample Questions for PS C_TS412_2021 Certification to test your understanding
of SAP C_TS412_2021process with real SAP certification exam environment.
C_TS412_2021S/4HANA Project Systems Sample Questions:-
01. You
have implemented automatic requirements grouping for projects. Once you check
the materials cabin and fork you realize that the requirements are grouped for
cabin but not for fork.
What
might be the reason?
Please
choose the correct answer.
a) The grouping indicator of the top WBS
element is set to a single MRP Group.
b) The network is set to no grouping for
specific MRP Groups.
c) The MRP Group for fork is deactivated for
grouping.
d) The project definition is set to no project
stock.
Answer: c
02. You
want to maintain basic data and dates of a WBS element on the same tab. Also,
basic start and basic finish should be mandatory fields. What do you need to
configure?
There
are 2 correct answers to this question.
a) Define Layout Detail Screen for the WBS
element to specify customer-specific tabs.
b) Define Create User-Defined Fields for the
WBS element to specify the mandatory fields.
c) Define Field Selection for the WBS element
to specify the mandatory fields.
d) Define Table Settings for the WBS element
to specify customer-specific tabs.
Answer: a, c
03.
Most of the reports in SAP Project System can be refreshed without exiting or
closing the report. Which report must be restarted to update the displayed
data?
Please
choose the correct answer.
a) Hierarchical Reports
b) Individual Overviews
c) Reports by Cost Element
d) Structure Overview
Answer: a
04. You
have created a network with planned work for internal activities. In a capacity
planning report, you discover that no capacity requirements were determined.
What
are the possible reasons for this?
There
are 3 correct answers to this question.
a) A work center has not been assigned to the
activity.
b) The work center does not contain any
available capacity data.
c) The wrong activity type category is entered
in the activity.
d) The indicator that calculates capacity
requirements is deactivated in the header of the network.
e) The capacity distribution key field is
empty.
Answer: a, b, d
05. You
want to confirm working hours to a WBS element using SAP Cross Application Time
Sheet (SAP CATS). However, once you enter the WBS element and the working hours
in SAP CATS you receive an error message. What could be the reason?
Please
choose the correct answer.
a) The system status "created" is
active.
b) The system status "master data
locked" is active.
c) You are not the responsible person for that
WBS element.
d) The confirmation exceeds the budget
assigned to the WBS element.
Answer: a
06.
What is copied when transferring a simulation version back to an operative
project?
There
are 3 correct answers to this question.
a) Plan costs
b) WBS elements
c) Actual work
d) Maintenance orders assigned to the project
e) Network activities
Answer: a, b, e
07.
When using budgeting and active availability control, which business
transactions affect the current budget?
There
are 3 correct answers to this question.
a) Cost element planning
b) Original budget
c) Revenues
d) Transfers
e) Supplements
Answer: b, d, e
08. You
have created a network with successive activities. After scheduling the
network, the Gantt chart shows that every activity has the same earliest start
and earliest finish date as the network header. What could be the reason?
Please
choose the correct answer.
a) The control key is set to no scheduling.
b) The scheduling type is set to capacity
requirements only.
c) The normal duration of each activity is
missing.
d) There is a loop in the network.
Answer: b
09. How
can material components be assigned to network activities?
There
are 3 correct answers to this question.
a) Using manual assignment.
b) Using the bill of materials transfer.
c) Using assigned sales orders.
d) Using Project-Oriented Procurement
(ProMan).
e) Using the Internet-based catalog.
Answer: a, b, e
10. You
want to extrapolate basic dates from lower to higher-level WBS elements. The
duration of higher-level elements should NOT be reduced. Which planning method
do you choose?
Please
choose the correct answer.
a) Bottom-up
b) Strict bottom-up
c) Free planning
d) Top-down
Answer: a